DOGGER BANK A & B ON SHORE WIND FARM
|
Albert Innes were proud to be involved with the world's largest off shore wind farm project which will generate enough power to serve 6 million homes.
The Valve Hall and Service building electrical installation, comprised on a new mains distribution system, LED lighting and controls, LED emergency lighting, LED external lighting, general power installations, cableway containment systems for the fibre/data cable infrastructure, security system, pneumatic pipeworks and DC cables. The electrical installation comprised of a mains distribution system, LED lighting and controls, LED emergency lighting, LED external lighting, general power installations, cabling containment for the sub mains, fire alarm system, data cable infrastructure, AV systems and mechanical supplies. |
MAIN CONTRACTOR:
Hitachi
|
client:
SSE
|
project value:
1.6 Million
|
Project duration:
60 weeks
|